Skip to content

Getting paid in Québec: notice of contract, legal hypothec and releases — the calendar not to miss

When to declare your contract, the 30 days to register the legal hypothec, the 6 months to preserve it, and what holdbacks and releases are really worth.

CompliancePublished September 8, 202611 min readThe BatiCore team

A contractor who is not paid rarely loses their money in front of a judge. They lose it in a calendar — that of the construction legal hypothec, which runs on its own, without notice, and which extinguishes a perfectly valid claim because a date has passed. Thirty days here, six months there, and a written notice that had to go out before the first hammer blow.

This guide lays that calendar flat: who must declare their contract and when, what must be registered in the land register within thirty days of the end of the work, what must follow within six months, how holdbacks and releases really work in Québec — and what the new prompt-payment regime changes, having just extended to medium-sized public contracts.

The calendar at a glance

WhenWhatIf you miss the date
Before your workDeclare your contract in writing to the owner (if you did not contract with them)No legal hypothec for what was supplied before the notice
DuringKeep proof of receipt of the notice, delivery slips, timesheetsThe declaration exists but you cannot prove it
30 days after the end of the workRegister the notice of legal hypothec in the land register and have it served on the ownerThe hypothec disappears — only a personal claim remains
6 months after the end of the workPublish an action against the owner or register a prior notice of exerciseThe registered hypothec is extinguished on its own
3 yearsPersonal action against your debtor (ordinary prescription)The claim is prescribed
The date that counts is not that of your invoice. All these deadlines run from the end of the work — not from the end of your invoicing, nor from the day the client stopped answering your emails. A claim unpaid for eight months can be past the hypothecary deadline while you still believe you are negotiating.

Step zero: the declaration of contract

The construction legal hypothec benefits, under article 2726 of the Civil Code, the architect, the engineer, the supplier of materials, the worker, the contractor and the subcontractor. But article 2728 sets a condition for those who did not contract directly with the owner — so for every subcontractor and every supplier: they must declare their contract in writing to the owner of the immovable. Only the worker is exempt.

The consequence is brutal and often misunderstood: the hypothec only secures what was supplied after the notice. A subcontractor who declares their contract the day they send their formal notice has nothing left to secure — the work is behind them. The declaration is a start-of-job gesture, not an end-of-job one.

What the notice must contain

  • The nature of the contract you concluded and with whom you concluded it (the general contractor, most often);
  • The price agreed, or an assessment of the value of the work or materials;
  • The description of the immovable concerned, as precise as possible;
  • Your intention to avail yourself of the legal hypothec if you are not paid.
Prove receipt, not just sending. The courts have looked more than once at perfectly drafted declarations that the contractor could not establish had reached the owner. Registered mail, bailiff, or a signed acknowledgement of receipt — the cost is trivial compared to the claim it protects.

Article 2727 sets out the mechanics. Your hypothec already exists, without any formality, during the thirty days following the end of the work. For it to survive that period, you must, before it expires, register in the land register a notice describing the immovable and stating the amount of the claim. That notice must also be served on the owner — in practice, by bailiff.

When those thirty days begin

"End of the work" does not mean "end of my own work". Within the meaning of article 2110, the work is completed when it has been carried out and is fit for use for its intended purpose — correcting minor deficiencies does not push that date back, and a professional certificate does not necessarily set it. Since the question gets litigated, the only prudent conduct is to count from the day you finished: you register earlier, therefore never too late.

What the hypothec secures is not your invoice, but the added value brought to the immovable by your work or materials. A contract balance, a holdback and essential costs are normally part of it; work that added nothing to the value of the immovable is not.

The six months: the step almost everyone forgets

Registering the notice is not enough. The hypothec is extinguished six months after the end of the work unless, within that period, you have published an action against the owner or registered a prior notice of exercise of a hypothecary right. Many contractors register their notice correctly, start a negotiation that drags on, and discover in the seventh month that their security evaporated while they were talking.

A negotiation suspends no deadline. If the discussion drags on, register the prior notice or file the action: nothing prevents you from continuing to negotiate afterwards, and you keep your security.

Past that point, not everything is lost — there remains the personal claim against the party you contracted with, subject to the three-year prescription, and recourse to the performance or payment bond where one exists. But you lose what made the hypothec strong: a right on the immovable, which blocks a sale or a refinancing and suddenly makes the conversation very concrete.

Holdbacks and releases: what the law really imposes

It is the most widespread source of confusion, especially among contractors who have worked elsewhere in Canada. Québec imposes no statutory holdback on private job sites. In Ontario, a 10% holdback applies by default; here, the 5% to 10% holdback you know is contractual — it exists because your contract says so, and it is released according to what your contract provides.

Two provisions of the Civil Code are added to the contract, and they play in opposite directions depending on which side of the table you sit on:

  • Article 2111 — the client may hold back, at acceptance, an amount sufficient to have the apparent poor workmanship corrected.
  • Article 2123 — at the time of payment, the client may hold back an amount sufficient to pay the claims of the workers and of those who declared their contract to them. That holdback stands as long as the contractor has not handed over a release of those claims; it falls if the contractor provides sufficient security.
Your subcontractors' declarations work against your collection. Every notice received by your client authorizes them to hold back. That is why releases are not paperwork: they are the key that frees your own money. An organized general contractor collects the release at the same time as they pay, never three months later.

What changes in 2026: prompt payment for public contracts

The Regulation respecting prompt payment and prompt dispute resolution for construction work has been in force since September 8, 2025. It applies only to public contracts — a private residential job site is not covered — but its progressive rollout brings a growing number of businesses into a regime where payment deadlines stop being negotiable.

FromBuilding contractsCivil engineering contracts
September 8, 2025Over $750,000Over $2,500,000
September 8, 2026From $75,000 to $750,000From $675,000 to $2,500,000
September 8, 2027All contractsAll contracts

The regime rests on a cascading payment calendar: the public body pays at the latest on the last day of the month; the general contractor pays its subcontractors on the fifth day of the second month following their request; the subcontractor pays its own on the tenth day, and each lower level has five more days. A refusal to pay must be signified by a reasoned notice within the prescribed period — failing which, the payment request is deemed valid.

In case of a dispute, an adjudicator decides in about fifty days, with a possible extension. Their decision binds the parties and must be executed, without being final: the ordinary civil recourse remains. It is a reversal of logic — silence no longer protects the one who does not pay.

What it changes concretely. On a covered public contract, your payment request becomes a dated document that starts an enforceable clock. Date it, keep proof of transmission, and watch the refusal date: past that date without a reasoned notice, your request stands.

An example, end to end

Fictional figures, real sequence. An excavation contractor signs a $46,000 subcontract with a general contractor for a new residence. They do not know the owner.

  • Before mobilizing — they send the owner a declaration by bailiff: nature of the contract, name of the general contractor, price of $46,000, description of the lot, intention to avail themselves of the legal hypothec. Cost: a few tens of dollars.
  • Their work ends on May 12, but the job site continues. They invoice, follow up, get promises.
  • On June 8 — twenty-seven days after the end of their work — they have the notice of legal hypothec registered and served on the owner. They do not wait to find out when the whole project will be completed: they count from their own end of work.
  • The balance remains unpaid. On November 2, before the six-month deadline, they register a prior notice of exercise. The discussion, polite until then, settles in three weeks: the immovable was about to be refinanced.

Without the initial declaration, that subcontractor had no hypothec to register. Without the November prior notice, their June registration became ineffective on November 12.

What BatiCore does for you

BatiCore does not draft your deeds — the declaration, the registration and the prior notice remain legal acts, often carried out by a bailiff or a notary. What the tool does is keep you from missing the date. Every project carries its declarations and its releases with their deadlines, the Payment protection tab shows who declared what and what remains to be released, and the schedule surfaces the dates that are approaching instead of letting them sleep in a binder. Holdbacks are tracked per invoice and per project, and each subcontractor's file says whether their compliance is up to date before you pay them. For the mechanics of holdbacks at invoicing, see Construction estimate template for Québec.

This text is general information, not legal advice. The legal hypothec deadlines are strict and their application depends on the facts of each job site: facing a large balance, consult a lawyer or a notary before the thirty-day deadline, not after.
Don't count the days by hand. The legal hypothec calendar takes your end-of-work date, gives the thirty-day and six-month deadlines, warns you if one of them falls on a day the register is closed, and puts the reminders in your calendar.
Sources consulted on September 8, 2026

The amounts and rules cited are those displayed by these bodies on that date; they change (indexation, decrees). Check at the source before acting — and this article is not legal advice.

See BatiCore on your own figures

Free 14-day trial, no credit card — create a real estimate today.

Frequently asked questions

What is the deadline to publish a construction legal hypothec in Québec?

Thirty days following the end of the work. During those thirty days, the hypothec exists without any formality; for it to survive, before the deadline expires you must register in the land register a notice describing the immovable and stating the amount of the claim, then have it served on the owner — in practice by bailiff. Then the hypothec is extinguished six months after the end of the work unless an action against the owner is published or a prior notice of exercise of a hypothecary right is registered. Both deadlines are strict: once past, the security disappears, even if the claim is perfectly valid.

Who must declare their contract to the owner?

Anyone who did not contract directly with the owner of the immovable and wants to avail themselves of the legal hypothec: subcontractors at every level and suppliers of materials. Only the worker is exempt. The notice must be in writing and state the nature of the contract, with whom it was concluded, the agreed price, the description of the immovable and the intention to avail oneself of the hypothec. Crucial point: the hypothec only secures what was supplied AFTER the notice — the declaration is therefore a start-of-job gesture, never a reaction to non-payment. Keep proof of receipt, not just of sending.

Is there a statutory 10% holdback in Québec?

No, not on private job sites. Unlike Ontario, where a 10% holdback applies by default, the 5% to 10% holdback practised in Québec is purely contractual: it exists because the contract provides for it and is released under its conditions. Two articles of the Civil Code are added to it: article 2111 allows the client to hold back enough to correct the apparent poor workmanship at acceptance, and article 2123 allows them to hold back enough to pay the claims of workers and of those who declared their contract — a holdback that stands as long as the contractor does not hand over a release of those claims, and falls if they provide sufficient security.

What is the prompt-payment regime and who is covered?

The Regulation respecting prompt payment and prompt dispute resolution for construction work, in force since September 8, 2025, imposes a cascading payment calendar in PUBLIC CONTRACTS — private job sites are not covered. It first applied to building contracts over $750,000 and civil engineering contracts over $2,500,000; since September 8, 2026 it also covers buildings from $75,000 to $750,000 and civil engineering from $675,000 to $2,500,000; on September 8, 2027 it will apply to all contracts. A refusal to pay must be the subject of a reasoned notice within the prescribed period, failing which the claim is deemed valid, and an adjudicator settles disputes in about fifty days.

What if the 30-day deadline has already passed?

The legal hypothec is lost, but not the claim. There remains the personal claim against the party you contracted with, subject to the three-year prescription, and recourse to the performance or payment bond where one exists — frequent on public and institutional job sites. What you lose is the leverage: a right registered on the immovable blocks a sale or a refinancing, which settles many files without ever going before a judge.

The BatiCore team

We build BatiCore, management software for Québec construction contractors — estimates, job sites, CCQ payroll, compliance. Our articles cite dated public sources; when a fact comes from a regulator or a competitor, we say which one and when. Spotted an error? Write to us, we fix it.

Share
Was this page helpful?

Also worth reading

All articles →