Hiring a subcontractor in Québec: RBQ licence, CCQ and CNESST — what to check before paying

RBQ licence and subclass, wages owed (CCQ), CNESST premium, GST-QST and T5018: what the laws say and what the attestations are really worth.

CompliancePublished October 25, 20269 min readThe BatiCore team
A general contractor and a subcontractor talk over drawings on a wood-frame job site.

Hiring a subcontractor means buying work. In Québec, it also means taking on a share of their risks: the wages of their workers, their CNESST premium, and the licence that allows them to do the work. Three laws deal with it, each in its own way, and they have one thing in common: you look at them before signing and before paying, not on the day a problem shows up.

This guide goes through what the texts say, the documents that inform you — the CCQ status letter, the CNESST attestation, the RBQ register — and their limits, because none of them removes the risk on its own. For the other side of the table, the subcontractor who wants to get paid, see Getting paid in Québec.

The overview at a glance

The topicWhat the law saysWhat informs youIts limit
RBQ licenceA contractor may not use the services of another contractor who has no licence for that workThe RBQ register of licence holdersIt takes the right subclass, and a licence in force during the work
Wages of their workersThe wages they owe are a solidary debt with the contractor who hired themThe CCQ status letterA snapshot at its date; it waives no recourse
Their CNESST premiumThe CNESST may claim it from whoever retains their servicesThe CNESST compliance validationIt does not release the principal
GST and QSTWithout a registered supplier, GST paid cannot be recoveredThe CRA registry and the Revenu Québec serviceCheck once, then if the number changes
T5018Payments for construction services are reported to the CRAYour own payments for the year6 months after the end of the period

Before signing: the licence, and the right subclass

Section 46 of Québec's Building Act is short. Its first paragraph prohibits acting as a contractor without a licence; the second one is aimed directly at you: no contractor may use, for the performance of construction work, the services of another contractor who does not hold a licence for that purpose.

"For that purpose" matters. A licence only covers its subclasses: a contractor licensed for wood framing is not, for that reason alone, licensed for excavation or roofing. The RBQ repeats it in every warning: before signing, make sure the contractor holds a valid licence and the appropriate subclasses. Its online register of licence holders shows it, along with the claims against the bond and the compensation paid over the last five years.

Check at signing, then during the work. A licence can be suspended or stop having effect along the way. It is also what protects the client owner against the wage debt described below: the CCQ states that the owner is not exposed to it if they make sure their contractor holds an appropriate licence, valid throughout the work. The subclasses are detailed in our RBQ licence guide.

Their workers' wages: solidarity under Act R-20

Section 54 of Act R-20 makes the wages owed by a subcontractor a solidary obligation between them and the contractor they contracted with — and, further up the chain, with the subcontractor who hired them, the contractor and any intermediate subcontractor. In practice: if your subcontractor does not pay their workers, the CCQ can claim those wages from you.

  • When your subcontractor holds their licence, that solidarity ends six months after the end of their work — unless, before that deadline, an employee has filed a complaint with the CCQ, a civil action has been brought, or the CCQ has sent a claim.
  • When they do not, the solidarity also extends to the client who contracted with them, directly or through an intermediary, for the wages owed by that contractor and by each of their subcontractors.

The CCQ status letter

This is the document that informs you about that risk. Your subcontractor requests it for their own file, in the CCQ online services, if they are registered as an employer; it costs $30. It is requested for bidding purposes or for the work on a specific job site, and it shows, among other things, the status of their monthly reports, civil claims, work-stoppage orders, penal convictions and whether they hold an RBQ licence.

A snapshot, not a release. The CCQ specifies that the letter in no way constitutes a waiver of its recourses. It tells you where your subcontractor stands at its date: ask for it at the bid, then for the job site before the large payments, and read it in full, including the part on their own subcontractors.

Their CNESST premium: section 316

The Act respecting industrial accidents and occupational diseases goes further. Its section 316 allows the CNESST to require the employer who retains the services of a contractor to pay the premium owed by that contractor. It may even compute it from the part of the agreed price that corresponds to labour, rather than from the wages declared.

Two sentences of the same section work in your favour. If you pay that premium, you are entitled to be reimbursed by the contractor, and you may withhold the amount from the sums you owe them. And when you show that you retain their services, the CNESST may tell you whether a premium is owed.

What the attestation is worth

Your subcontractor can ask the CNESST for a compliance validation: the answer can be used to bid or to show their compliance to a third party. But the CNESST form says it plainly: the answer does not release a principal from paying the premium owed by the contractor, under section 316.

The document informs you; it does not protect you. That is precisely why it is checked at the right moments: at the start of the contract, then before each large payment and before the last one. If a doubt remains, section 316 lets you withhold the amount at stake rather than pay first and claim afterwards.

Comparing prices on the same scope

Many bad surprises start at the bid, when two prices do not cover the same thing. Before comparing, bring every offer back to the same scope:

  • the same drawings and addenda, named in the offer;
  • what is included and what is excluded, line by line — the lowest offer is sometimes the one that excludes the most;
  • the schedule and how long the price is valid;
  • taxes: a price before taxes and a price including taxes cannot be compared.

The written contract then restates that scope, the price, the schedule and the holdback. On a private job site, no law sets a holdback percentage: the 5% or 10% holdback you know exists because the contract provides for it. On the client's side, the Civil Code only speaks of a "sufficient amount" for the claims of workers and of those who declared their contract to the client — the details, with releases, are in Getting paid in Québec.

When paying

  • The attestations, still valid on the payment date. An attestation that expired the day before no longer tells you anything.
  • The release, collected as you pay. Their suppliers and their own subcontractors who declared their contract to the owner are entitled to the legal hypothec on the immovable, and the owner may withhold from what they owe you until they have the release of those claims.
  • GST and QST numbers. The CRA puts it simply: use its GST/HST registry to confirm that the business charging you the tax is registered; otherwise, you will pay the tax without being able to claim input tax credits. Revenu Québec, for its part, offers a service to check the validity of a QST registration number.
  • The T5018. If more than half of your business activity is construction, the CRA requires a T5018 slip for each subcontractor you paid more than $500 for construction services in the period, not including GST/HST. Payments for goods only are not reported. The return is filed within 6 months after the end of the period you chose: the calendar year or your fiscal period.

An example, end to end

Fictional figures, real sequence. A general contractor hires a roofer for a $38,000 contract before taxes on a commercial building.

  • At the bid — they look the roofer up in the RBQ register: licence in force, roofing subclass on file, no recent claim. They ask for their CCQ status letter for bidding purposes and their CNESST compliance validation.
  • At signing — the contract restates the drawings, the two addenda, the exclusions, the schedule and a 10% holdback released with the final release. They check the GST and QST numbers once.
  • At the third payment — the CNESST attestation expired a week ago. They ask for the new one before paying; it arrives two days later.
  • At the last payment — they get the CCQ letter for this job site and the final release, then release the holdback.
  • The following year — their reporting period is the calendar year: they file their T5018 slips by June 30.

None of this takes long. What is costly is doing it after the fact: an attestation requested three months after the payment says nothing about the situation on the day you paid.

What BatiCore does, and what it does not

BatiCore checks nothing with the RBQ, the CCQ or the CNESST: it keeps what you enter, or what your subcontractor uploads, and reminds you at the right moment. In practice:

  • one record per company, in the directory: RBQ number, CNESST attestation and liability insurance with their validity dates, reused by every project;
  • the CCQ status letter noted for each project, and a Compliance column showing who is up to date, who expires within 30 days and who has expired;
  • when recording a payment, a reminder of what is missing — expired attestation, missing letter, expired insurance. BatiCore does not block: you may have the document in hand;
  • releases and the holdback released with the final release, on paper on every plan, and signed online by the subcontractor in their portal from the Business plan;
  • calls for bids (Business plan): one price request to several companies, and their offers compared on the same scope, with a warning when the lowest excludes what others include;
  • the year's total paid to each company, across all projects — the basis of your T5018 slips.
This text is general information, not legal or tax advice. Every contract has its own facts: faced with a subcontractor in difficulty or a large balance, consult a lawyer or your accountant before paying.
Sources consulted on October 25, 2026

The amounts and rules cited are those displayed by these bodies on that date; they change (indexation, decrees). Check at the source before acting — and this article is not legal advice.

See BatiCore on your own figures

Free 14-day trial, no credit card — create a real estimate today.

Frequently asked questions

Can I hire a subcontractor who has no RBQ licence?

No, not for construction work. Section 46 of Québec’s Building Act says that no contractor may use, for the performance of construction work, the services of another contractor who does not hold a licence for that purpose. The licence must cover the subclass of the work entrusted. The RBQ register of licence holders shows it online, with the claims against the bond over the last five years.

Am I liable for the wages my subcontractor owes their workers?

Yes, solidarily. Under section 54 of Act R-20, the wages owed by a subcontractor are a solidary obligation with the contractor who hired them and any intermediate subcontractor. If the subcontractor holds their RBQ licence, that solidarity ends six months after the end of their work, unless a complaint, a civil action or a CCQ claim comes before that deadline. If they hold no licence, it also extends to the client who contracted with them.

What is the CCQ status letter for?

To assess the risk of a claim for unpaid wages. The subcontractor requests it for their own file in the CCQ online services, for bidding purposes or for a specific job site; it costs $30. It shows, among other things, the status of their monthly reports, civil claims, work-stoppage orders, penal convictions and whether they hold an RBQ licence. The CCQ specifies that it is not a waiver of its recourses: it is a snapshot at its date.

Does the CNESST attestation protect me if my subcontractor does not pay their premium?

No. Section 316 of the Act respecting industrial accidents allows the CNESST to require whoever retains the services of a contractor to pay the premium owed by that contractor, and the CNESST compliance validation form specifies that the answer does not release the principal. The same section, however, lets you be reimbursed and withhold the amount from what you owe the subcontractor. The attestation informs you: check it at the start of the contract and before each large payment.

Who must file the T5018 slip, and when?

Any business for which construction is more than half of its activity, for each subcontractor it paid more than $500 for construction services in the period, not including GST/HST. Payments for goods only are not reported. The return is filed with the CRA within 6 months after the end of the chosen period: the calendar year or the fiscal period.